【Summary】The main focus is to explain the functions of each button on the machining center's operation panel, enabling students to master the adjustments of the machining center, the preparatory work before processing, and the methods for inputting and modifying programs. Finally, using a specific part as an example, the basic operation process of machining parts on the machining center is explained, giving students a clear understanding of the operation of the machining center. 1. Machining Requirements Machining the part shown in the figure below. The material of the part is LY12, produced as a single piece. The part blank has been machined to Size. Selected equipment: V-80 machining center 2. Preparatory Work Complete relevant preparatory work before machining, including process analysis and process route design, selection of tools and fixtures, program preparation, etc. 3. Operating Steps and Content 1) Power on, manually return each coordinate axis to the machine tool origin. 2) Tool Preparation Select one Φ20 end mill, one Φ5 center drill, and one Φ8 twist drill according to the machining requirements, then clamp the Φ20 end mill with a spring collet tool holder, set the tool number to T01, and clamp the Φ5 center drill and Φ8 twist drill with a drill chuck tool holder, setting the tool numbers to T02 and T03, respectively. Install the tool edge finder on the spring collet tool holder, setting the tool number to T04. 3) Manually place the tool holder with the installed tools into the tool library, that is: 1) Input "T01 M06" and execute. 2) Manually install tool T01 onto the spindle. 3) Sequentially place T02, T03, and T04 into the tool library following the above steps. 4) Clean the workbench, install the fixture and workpiece. Clean the bench vise and install it on a clean workbench, then use a dial indicator to align and level the vise, and install the workpiece in the vise. 5) Tool Setting, Determine and Input Workpiece Coordinate System Parameters 1) Use the edge finder to set the tool, determine the zero offset values in the X and Y directions, and input the X and Y zero offset values into the workpiece coordinate system G54, with the Z direction zero offset value input as 0; 2) Place the Z-axis setter on the upper surface of the workpiece, retrieve tool 1 from the tool library and install it on the spindle, use this tool to determine the Z direction zero offset value of the workpiece coordinate system, and input the Z direction zero offset value into the corresponding length compensation code of the machine tool. The “+” or “-” sign is determined by G43 or G44 in the program. If the length compensation instruction in the program is G43, input the “-” Z direction zero offset value into the corresponding length compensation code of the machine tool; 3) Input the Z direction zero offset values of tools 2 and 3 into the corresponding length compensation codes of the machine tool using the same steps. 6) Input Machining Program Transfer the computer-generated machining program to the memory of the machine tool's CNC system via a data cable. 7) Debugging the Machining Program Debug using the method of translating the workpiece coordinate system along the +Z direction, i.e., lifting the tool. 1) Debug the main program, checking whether the three tools complete the tool change actions according to the process design; 2) Debug the three subprograms corresponding to the three tools, checking whether the tool actions and machining paths are correct. 8) Automatic Machining After Confirming the program is correct, restore the Z value of the workpiece coordinate system to its original value, set the rapid movement multiplier switch and cutting feed multiplier switch to low gear, press the CNC start button to run the program, and begin machining. During the machining process, pay attention to observing the tool trajectory and remaining movement distance. 9) Remove the workpiece and conduct inspection. Use a caliper for size detection, and perform quality analysis after inspection. 10) Clean the machining site. 11) Power off.

                                                                        CNC machining process of parts

This mainly explains the functions of various buttons on the machining center operation panel, enabling students to master the adjustments of the machining center, the preparation work before processing, and the methods for inputting and modifying programs. Finally, using a specific part as an example, the basic operation process of machining parts on the machining center is explained, giving students a clear understanding of the operation of the machining center.

1. Processing Requirements

Process the part shown in the figure below. The material of the part is LY12, produced as a single piece. The part blank has been machined to size.

Selected equipment: V-80 machining center

2. Preparation Work

Complete relevant preparation work before processing, including process analysis and process route design, selection of tools and fixtures, program preparation, etc.

3. Operating Steps and Content

1. Turn on the machine, manually return each coordinate axis to the machine tool origin.

2. Tool Preparation

Select one Φ20 end mill, one Φ5 center drill, and one Φ8 twist drill according to the processing requirements. Then, clamp the Φ20 end mill using a spring collet tool holder, setting the tool number to T01. For the Φ5 center drill and Φ8 twist drill, use a drill chuck tool holder, assigning the tool numbers T02 and T03 respectively. Finally, install the tool edge finder onto the spring collet tool holder, setting its tool number to T04.

3. Manually place the tool holder with the clamped tools into the tool library, that is,

1) Input "T01 M06" and execute.

2) Manually install tool T01 onto the spindle.

3) Sequentially place T02, T03, and T04 into the tool library following the above steps.

4. Clean the workbench, install fixtures and workpieces.

Clean the bench vise and place it on a clean workbench, use a dial indicator to align and level the vise, then install the workpiece in the vise.

5. Tool Setting, determine and input the workpiece coordinate system parameters.

1) Use the edge finder to set the tool, determine the zero offset values in the X and Y directions, and input the zero offset values in the X and Y directions.

Input into the workpiece coordinate system G54, with the Z direction zero offset value input as 0;

2) Place the Z-axis setter on the upper surface of the workpiece, retrieve tool number 1 from the tool library and install it on the spindle, use this tool to determine the Z direction zero offset value of the workpiece coordinate system, and input the Z direction zero offset value into the corresponding length compensation code of the machine tool. The "+" and "-" signs are determined by G43 and G44 in the program. If the length compensation instruction in the program is G43, input the "-" Z direction zero offset value into the corresponding length compensation code of the machine tool.

3) Input the Z direction zero offset values of tools 2 and 3 into the corresponding length compensation codes of the machine tool using the same steps.

6. Input the processing program.

Transfer the computer-generated processing program to the memory of the machine tool's CNC system via a data cable.

7. Debug the processing program.

Debug using the method of translating the workpiece coordinate system along the +Z direction, that is, raising the tool.

1) Debug the main program, check whether the three tools complete the tool change actions according to the process design;

2) Debug the three subprograms corresponding to the three tools separately, checking whether the tool actions and processing paths are correct.

8. Automatic Processing

After confirming that the program is correct, restore the Z value of the workpiece coordinate system to its original value, set the rapid movement multiplier switch and cutting feed multiplier switch to low gear, press the CNC start button to run the program, and begin processing. During processing, pay attention to observe the tool trajectory and remaining movement distance.

9. Remove the workpiece and conduct inspection.

Use a caliper for size detection, and conduct quality analysis after inspection.

10. Clean the processing site.

11. Turn off the machine.